This is the page that will give any information regarding the maintenance and paving of the roads.
We hope this will be helpful to you. Much of this information will be in .pdf format
to retain any formatting that might be pertinent to the information.
It's also easily printed.

The HPPOA Board of Directors, Management and Staff

 

Paving Information as of March 12, 2008 (pdf. file)

UPDATE: April 20, 2008

Rough survey for the Makuu to Paradise portion of 22nd Avenue was accomplished on 3/31 and 4/1 2008. Mobilization of grading equipment took place on 4/9 and clearing and shaping of roadway commenced 4/10 to 4/16. Base rock and final shaping of the roadway will take place starting 4/21 with expectations of paving to begin 4/23,24 or 25.

UPDATE: May 20, 2008

The completion of the Hot Mix Asphalt (HMA) application portion was completed on 5/1/2008 with gravel installation at the shoulder and clean up of right of way through 5/7/2008.

Clearing and grubbing was started on 5/8/2008 and continued through 5/13/2008 when a preliminary evaluation of areas of concern were identified for installation of larger base material were to be applied. Installation of final base application started on 5/19/2008 to achieve shaping of the right of way and acceptance by the Civil Engineer before proceeding with the application of the HMA. Application of the HMA is projected to start between 5/22/2008 and 5/27/2008 with completion dependent on availability of HMA product from the supplier on a daily basis.

UPDATE: December 24, 2008

Paving info 12-24-08.pdf